New Building Plans

Story Here

WORK LIST

TASK

DONE BY

PRIORITY

DEPENDENCY

Interior Tasks




Bring floor in back up to level or lower dock

4C

Must be completed before occupation

Drawings from Traditional Designs

Two x ADA-compliant bathrooms

4C

Must be completed before occupation

Floor to code in lean-to

Remove fences and shed outside




Remove Fence around parking lot

V

ASAP

None

Remove Shed in parking area

V

ASAP

None

Remove Fence house / church building

V

Can be done at any time

None

Install fence along front of property

River

Can be done at any time

Removal of weeds and trash in area

Outdoor Features




Weed / remove trash from parking area

V

ASAP

None

Weed outside other than parking area

V

Ideally done prior to occupation

None

Cut down tree and ground out stumps

Uribes

$3800

December – Earlier if they get a cancellation

None

Pave and paint parking area. Install Handicap sign and parking blocks.

River

$9500

Must be completed before occupation

Negotiate options with City

Removal of Back Fence , Shed

Removal of tree roots, cement slabs

Install sidewalk / gardens around building

River

Can be done any time

Pending decision of which method

Playground

River

Ideally done prior to occupation

Purchase decisions to be made

SIGNS




Install “Future home of” sign on building.

River

ASAP

Acquire banner

Install permanent sign on building

4C?

Ideally done prior to occupation

Completion of exterior walls rehab

Irrigation for grounds




Locate irrigation connection

River

Can be done any time (Goal – 30 days?)

Coordinate with City

Design/Install sprinklers and sprinkler control

River / V

Can be done any time (Goal – 60 days? Before ground freezes)

Are cleaned of debris and weeded

Remove construction debris from deck and tear down deck.

V

ASAP

Dump trailer to be on site?

Determine if second water meter is an option

Bill

ASAP

Byron might have to be in office to ask

Utilities




Install second electric meter

4C

60 days

In progress

Determine which are live and cut power to all church circuits.

4C

ASAP

Interior must be mostly cleaned out

Remove all wiring in church portion of building

V

ASAP

After electrician cuts power to all church circuits.

Wire Building

4C

Must be completed before occupation

Drawings from Traditional Designs

Wire for Audio / Visual

4C

Must be completed before occupation

Must be coordinated with David/Michael

Locate gas meter

River

ASAP

Deck to be cleared and removed

Cap old heater / connect to unused meter

4C

ASAP

Inside clean enough to provide access

HVAC

4C

May ideally be done prior to occupation

(option to use old gas heater this winter?)

Inside Cleaned Out

Drawings from Traditional Designs

Exterior Building Features




Remove vinyl siding from building

V

Ideally done prior to occupation

None (good weather?)

Install proper insulating wrap to exterior

4C

Ideally done prior to occupation

Vinyl siding must be removed

Relocate/ Replace / Install Doors

4C

Must be completed before occupation

Drawings from Traditional Designs

Replace Windows

4C

Must be completed before occupation

Drawings from Traditional Designs

Interior Building Features




Remove interior drywall and insulation.

V

ASAP (30 days?)

Interior must be mostly cleaned out

Insulate all walls

4C

Must be completed before occupation

Electrical work completed

Design/Build Stage/Baptismal

4C

Must be completed before occupation

Coordination of design